  • Acting for the operator of the KLIA water cooling plant in arbitration with a specialist contractor who was engaged to carry out overhauling works in respect of the Plant’s turbines.
  • Acting for a large development and construction company in arbitration with a main contractor on delay and termination issues.
  • Successfully acted for a sub-sub-contractor who supplied and installed pipe installations and materials in a power station project in arbitration, and in the High Court, Court of Appeal and Federal Court.